
Representatives of the various trades involved in the Memorial Union renovation project discuss their progress Monday morning in the Veterans Hall of Honor. The project should be finished in April. Chris Franklin/The Bulletin
After breaking ground in April 2010, the Memorial Union continues to be on track for a total makeover, which should be completed this coming April, according to Dave Hendricks, director of the Memorial Union.
“We’re over halfway (done), which is nice,” Hendricks said.
Hendricks said the project is moving along, but there is still much more that must be completed and some obstacles have come up.
Hendricks said that the current focus now is the third floor, which will house student publications and a senate chamber for the Associated Student Government. This work is scheduled to be completed sometime this semester.
“The areas that we’re working in right now are the most challenging for the contractor because they’re the oldest,” Hendricks said.
He said that much of the building dates back to 1925, which has added complications. There was a holdup with fire suppression systems and getting new plans approved and equipment installed.
The next area that is scheduled to go online is the west side of the lower level. This will include the entrance from the north side of the building, the Office of International Education and Career Services. Hendricks said that the nicest feature of this portion is the open stair tower. These stairs are concealed by glass so it will be possible to see up to the top from the lower level as well as down and outside.
“And then, unless something drastically happens, we’re on track to complete the main street area over the winter break,” Hendricks said.
The final portion of the renovations will include the Kanza, Flint Hills and Greek rooms which will go offline at the end of the semester.
“I’m excited to see how it turns out,” said Kaylynn Anderson, freshman secondary history education and Spanish major. “It’s kind of annoying right now because you have to walk around it and hear the noises.”
Originally, Hendricks said about $18 million was the estimated cost of “phase one” of the process. Since the first phase cost only $16 million, the union was able to initiate what Hendricks called “phase two” of the process, which included the third floor, everything west and north of the ballroom and some extra work on the lower level waterproofing.
“(It has) far, far, far exceeded any expectations that I had,” Hendricks said.
New features will include an updated main street, additions to the ballroom and a new “convenience” store, according to the ESU renovations website. Additional information and updates on the progress can be found at Emporia.edu/murenovation.
Brooke Schultz
























Recent Comments